The California Public Utilities Commission (CPUC) proposes to enhance the capabilities of the CPUC's existing Renewables Portfolio Standard Database.
| Agency / State Entity | General Government / Public Utilities Commission |
|---|---|
| Total Cost | $4,366,074 |
| Last Approved Start Date | 11/22/2022 |
| Last Approved Finish Date | 11/14/2025 |
| Criticality Rating | Medium |
| IPOR Reporting Period | Overall IPOR Rating |
|---|---|
| 12/01/2025 - 12/31/2025 |
Key Questions
Is the project on track to satisfy the customer's business objectives?Yes
Is the project on track to achieve the objectives in the approved timeframe?No
Is the project on track to achieve the objectives within the approved budget?Yes
| Project Overall Health | Comments |
|---|---|
| Special Project Report (SPR) was officially submitted in October 2025 and was approved during the reporting period. The newly established project baselines have moved the overall project from red to yellow. Project closure has been pushed to January 2026, for project to complete required deliverables and scope before transitioning into maintenance and operations (M&O). |
| Focus Area/Rating | Comments |
|---|---|
| Governance |
• Project roles and responsibilities are established and documented. • Executive Steering Committee (ESC) meetings have not been held since April 2025. • The Business Project Manager (PM) is actively engaged in current activities and decision-making. • Governance Plan is in place and processes are being followed. |
| Time Management |
• Project has exceeded the approved end date of November 14, 2025, by four percent (4%). • A schedule review meeting was held. • Schedule Management Plan is in place. |
| Cost & Contract Management |
• Current project costs are in alignment with approved budget. • IV&V contract ended November 20, 2025. • Contract and Cost Management Plans are in place. |
| Scope Management |
• One (1) Administrative CRs was submitted to descope requirements no longer needed, approval pending. • Need to ensure Change Management process continues as the project transitions to M&O. • Scope and Requirements Management Plans are in place, but processes are not being followed. |
| Resources |
• Contractor resource constraint risk has been realized, created delays to schedule. • The current project team appears to work well together. • There has been good representation from the business lead Subject Matter Experts (SME) in meetings. • Resources have the appropriate tools to complete project work. Need to ensure the continued use of the project’s tools as the effort transitions to M&O. • HR and Staff Management Plan is in place and being followed. |
| Quality |
• Backlog of bugs remained to be resolved pushing final production deployment to January 2026. • Presentations and demos created and delivered by contractor have been clean, neat, and well organized. • No deliverables were submitted and approved. • Quality Management Plan is in place and being followed. |
| Risk And Issues |
• Oversight unable to confirm risks and issues are being identified and tracked in accordance with the Risk and Issue Management Plans and bi-weekly meetings have been cancelled. • Risk and Issue Management Plans are in place but not being followed. |
| Transition Readiness |
• Overall project readiness is directionally positive but not yet acceptance ready. • Knowledge transfer has been planned and scheduled. |
| Conditions For Approval |
• There are no conditions associated with SPR 1. |
| Corrective Action |
• There are no corrective action plans in place. |