Independent Project Oversight Report (IPOR) Rating

8570-089 Emerging Threats 2 (ET2)

The California Department of Food and Agriculture, Animal Health and Food Safety Services (AHFSS) Division, is proposing to replace their existing Emerging Threats system to correct and eliminate multiple deficiencies that have arisen over the maintenance and operations life cycle of the system and to provide an enterprise-wide solution for all programs within the AHFSS Division.

Project Details

Agency / State Entity General Government / Food and Agriculture, Department of
Total Cost $50,178,609
Last Approved Start Date 12/04/2025
Last Approved Finish Date 12/29/2028
Criticality Rating High
IPOR Reporting Period Overall IPOR Rating
12/01/2025 - 12/31/2025
Green
Independent Project Oversight Dashboard

Key Questions

Is the project on track to satisfy the customer's business objectives?Yes

Is the project on track to achieve the objectives in the approved timeframe?Yes

Is the project on track to achieve the objectives within the approved budget?Yes

Project Overall Health Comments
Green
• The project kick-off was on 11 December 2025, and the project health for this period is GREEN. • A draft version of the Project Management Plan is being reviewed by the CDFA.
Focus Area/Rating Comments
Governance

green icon Green
• A Governance Structure has been agreed to and documented in the project planning process. IPO will be observing the plan in action to validate its effectiveness. • The Project Team is working through Project Team onboarding activities and is expected to schedule on-going Executive Steering Committee (ESC) Meetings with internal stakeholders and external stakeholders that includes the CDT and the DOF in the near future.
Time Management

green icon Green
• A high-level Roadmap was drafted. The schedule will be drafted and baselined after requirements are finalized. • IPO will monitor the Project’s execution and adherence to the plan as the project progresses.
Cost & Contract Management

green icon Green
• The Project has an approved Cost Management Plan and Contract Management Plan. • There have not been any vendor invoices paid to date. • IPO will monitor the Project’s execution and adherence to these plans as the Project progresses.
Scope Management

green icon Green
• The Project has an approved Scope Management Plan. • IPO will monitor the Project’s execution and adherence to the plan as the Project progresses.
Resources

green icon Green
• The Project has an approved Resource Management Plan. • The project team is staffed with resources and currently no vacancies or resource gaps exist.
Quality

green icon Green
• The Independent Verification and Validation (IV & V) contract was awarded with a start date of December 11, 2025. • The Project Management Services and Quality Assurance and Testing Services contracts were awarded with a start date of December 11, 2025. • IPO will monitor the Project’s execution and adherence to quality management as the Project progresses,
Risk And Issues

green icon Green
• The Project has an approved Risk and Issues Management Plan. • The Project Team has begun using a Risk and Issue Log to track risks and issues identified.
Transition Readiness

blue icon Blue
• The Project is in the beginning of the execution stage, and it is too early to evaluate the transition readiness of the organization.
Conditions For Approval

green icon Green
• Within 90 calendar days after November 21, 2025, Approval Letter, which is February 21, 2026, the CDFA shall develop and submit to the CDT an Integrated Master Project Schedule that incorporates both State and System Integrator (SI) deliverables, milestones, and activities. The schedule shall reflect a clearly defined and logical critical path and adhere to the Project Management Institute (PMI) Schedule Management best practices and California Project Management Framework (CA-PMF) standards. The schedule shall be developed and maintained using Microsoft Project. • No later than 60 calendar days prior to the initiation of testing activities by the SI, the CDFA shall submit the approved ET2 Project Test Management Plan to the CDT.
Corrective Action

green icon Green
• There are no corrective action plans in place.
Project Approval Documents

20250626 Release-16